We're prepped and ready for the concrete slab on Tuesday. It's been a delay of a week and a half. Slab was supposed to be poured on May 15th but the wind was really strong in the morning. The slab contractor was concerned the cement would dry/cure too fast and create spiderweb cracks on the top so it was postponed to the 22nd (last Friday). Again, it was blowing hard so now we're at Tuesday. The forecast looks good. Hindsight, we should have just done it on the 15th in the afternoon after the wind completely stopped.